Hello Experts,
The  issue is, let say we have 7 operation for producing particular SFG or FG. At operation 0030 some qty got rejected due to some reason. Now user want to put the rejected  qty in CO11N screen with reason of rejection and in next operation only accepted conformed qty will come.
Please give some solution to reject some unplanned qty at operation level with rejection reason.
Thanx in advance.
Regards,
Neha PP
Advertisement

Replay

Hello Experts,
The que is still open, i am explaining the requirement once again
i have 5 operations in my routing...... the production order is of 5000 pcs..... i confirmed 5000 pcs in operation 0010 & 5000 pcs in operation 0020. At operation 0030,  200pcs are rejected due to some reason so i confirmed only 4800 pcs & want to mention the 200 pcs as rejected qty at operation 0030.......... now the issue is  the rejection is unplanned, some time it may happend & some time it may not & it can be happend at any operation............
So in above said scenario where can i show in CO11N screen that 4800 pcs are confirmed & 200 pcs are rejected with reason at operation 0030.
Hope the issue is clare now.
Regards,
Neha_PP

How to confirm operation wise confirmation.

Hi,    please tell me how to confirm operation wise confirmation in details.        Thanks         paragHi Parag, Confirmation against a production order can be done in 2 ways : 1. Confirmation against each operation of an Order can be done  in Tcode

Change Routing Activity value during Operation wise confirmation (CO11)

Hello All, In Tool room scenario I need to carry out operation wise confirmation co11/co11n to know the order progress. However I need to update activity value (in routing) for each operation once the operation is finished physically. Is this possibl

Which table can give Operation wise Machine/Labour Std Value Time

Dear Sir, We need to know the Table name which can be used to get  Operation wise Machine/Labour Std Value Time for a given Production Order . Using CO03 . we can get Std Values displayed for the Machine/Labour Time by double click on the operation .

Scrap-co11n

Dear all, In co11n screen i enter the yield and scrap quantity.I am able to trace the yield quantity through 101 mov  but how can I trace the scrap quantity? Kindly helpHi , This entry is nothing but the process loss. If you  disply the confirmation

Operation wise Production Scheduling Graphical Report

Dear Expert , I have multiple production orders and each operations have schedule start date and finsihe date .My client wants a graphical bar chart or grarate chart of production oreds , operations schedule  based on  vaious work centers after doing

Good Movement at the confirmation of an operation

Dear All, I tried to make good movement when I maked an confirmation for an operation. I configured whit TC: OPK4 automatic good movement and whit TC: OP67 I choosed option automatic good movement for control key. However, when I maked an confirmatio

Scrap analysis report

Hello all, In transaction code co11n, we enter the scrap and the reason for variance. Do we have any std report which will give me the analysis of REASON WISE SCRAP for production orders. Thanking all in advance. Shivanigoto transaction COOIS select

Diff between CO11N & CO15?

Hi I am new to discrete manufacturing scenario......Can anyone tell me what is the difference between T Codes CO11N and CO15? As such both are used for confirmations..... Moreover what does this "time ticket" means? RgdsHi, If u want do confirma

Confirmation in co11 with scrap

Hi,    My client doing production confirmation in co11 ( operation wise)    they want enter scrap qty in confirmation and scrap material qty in 531 there itself    whether we can enter it in Goods movement screen in co11???? thanks in advancehi thanx

Equiment Maintenance (Elec + Mech operations)

Dear Experts, I need to discuss - like in case of transformer we have one month schedule maintenance, but this include  3 elec oper + 3 Mech oper. Now, both dptt may have to issue some material for the same. Cost center of mechanical & electrical Dpt

Day wise production order

Hi Gurus, Can any one please help me down?? Do we have standard SAP report to track on day wise production order status other than COOIS,CO26,CO28 and MD4C. Regards, VINODHPrasobh, My client needs to track the production order daywise... 1.The operat

CO11N confirmatiom Very very urgent

I'm trying to cofirm prodn order oprn wise, in CO11n screen goods movement screen in not displaying next to actual data button & also i'm getting the message goods movement failed, maintain stor locn. i'm using podn order with all components backflus

Attaching operations to Production Order or Routing

Hi All ,        We have a scenario where the user is  We're in need of setting up "Shop Floor transactions" for all production . This request is in order for production control and material management to have better control on Production Order m

Inprocess inspection

Hi experts One of my semifinished material i have routing with two operation from PP side . I add a new operation for QM inspection with Assign QM work center and assign inspection chracterestic in routing Now i have the following dout on this 1.What

Activity time

Dear All, Iam using milestone confirmation CO15, when I use this I would like to get the Planned time from the routing to be updated in AFRU table. I dont want to use CO11N -operation wise transaction for confirmation. Is it possible to update the pl

Confirmation of order

dear all,               can u pls let me know the difference between confirmation of order by CORK and COR6N in process industry. rgds AmitabhHi, CORK is used to confirm the whole process order. COR6N is used to enter the confirmation operation wise.

Notification quantity fields

Hi, Please clarify me on the actual purposes of quantity fields in notification like Complaint quantity, Refernce quantity, Defect quantity internal, Defect quantity external and Return Delivery quantity. Please throw some light with actual use of th

Configuration for shift repor and shift note

Hi all We have currently activated the shift report functionality of SAP . Does any can share the configuration details for PM module for the above as a reference With Regards ArunHi, Kindly apply SAP Note 1415590. The note is as below:- Solution 1.

Serial Number. Production Order Confirmation. GR. UD. Sales Delivery

Hi Gurus, Please help on this issue to get any user exits ..... As part of Serial number management, we have a certain issues on serial number confirmation, goods receipt from production order and quality inspection with UD. Master data: Finished pro